Which interfaces should be recorded?

Use the tender systems and parties as the starting point. Record interfaces between electrical, civil, mechanical, controls, suppliers, the client and commissioning team where the documents identify them.

Illustrative interface register
InterfaceQuestionClosure evidence
Power to controlsWho supplies the points list?Approved I/O schedule
Equipment to roomWho coordinates the outline?Reviewed arrangement
Install to testWho prepares the test record?Approved procedure
Construction to ownerWho assembles handover?Evidence index

How should an unclear interface be handled?

Record both documents, the unanswered question, interim action and owner. An interface stays open until the responsible team approves the boundary.

  • Name both parties
  • Cite the source documents
  • State the handover
  • Assign an owner
  • Define closure evidence

Why does the register matter to pricing?

A boundary can change quantity, programme, testing, labour and risk. Keeping it visible helps the estimate and response team update the bid when clarification arrives.

Common questions

What else should the bid team know?

What should a interface register record?

It should record the two parties, boundary, source, action, owner, due date and evidence needed to close the issue.

Who reviews a interface register?

The bid manager controls the register, while the affected technical and commercial leads approve their responsibilities.

Can this page replace the tender instructions?

No. The issued tender, its addenda and the responsible technical, commercial or legal reviewers control the final position.

Primary sources

  1. Commonwealth Procurement RulesAustralian Government Department of Finance
  2. Additional rules: request documentationAustralian Government Department of Finance
  3. The Construction PlaybookUK Cabinet Office
  4. FAR Part 15: Contracting by NegotiationAcquisition.gov