Which fields should an SDRL contain?

Start with the project's document numbering and submission rules. Add one row per required document, then record the required issue stage, reviewer and disposition.

Illustrative SDRL fields
FieldExample useControl
Document codeVendor drawing or manual IDUse the project code
DescriptionEquipment document titleMatch the specification
Required stageFor review or as builtUse the approved schedule
Due dateContract or programme dateRecord source
DispositionOpen, reviewed or acceptedKeep the review trail

Sources: Australian Government Department of Finance: Commonwealth Procurement Rules, Australian Government Department of Finance: Additional rules: request documentation

How is an SDRL different from a document register?

A document register records documents that exist or have been received. An SDRL records documents that a supplier is expected to produce and the review path for each one. A project may use both registers together.

  • SDRL: obligation and planned submission
  • Document register: received or issued file
  • Transmittal: a particular exchange of files
  • Review record: comments and disposition

What should happen when a document is late?

Keep the required date, current status, owner and effect on downstream work visible. Do not mark a document accepted because a related file has arrived.

Sources: UK Cabinet Office: The Construction Playbook

Common questions

What else should the bid team know?

Can a template replace the issued tender instructions?

No. The issued tender and its addenda control the required format, channel and deadline. Use a template as an internal control only.

Who approves the final bid position?

The bid team assigns technical, commercial and legal review to the appropriate people. A document register or checklist does not provide that approval.

What happens when the source documents conflict?

Keep both references visible, record the conflict and raise a clarification or internal review action. Do not silently choose one document.

Primary sources

  1. Commonwealth Procurement RulesAustralian Government Department of Finance
  2. Additional rules: request documentationAustralian Government Department of Finance
  3. The Construction PlaybookUK Cabinet Office
  4. FAR Part 15: Contracting by NegotiationAcquisition.gov